Establish a shared view of the work
A recovery plan needs a clear starting point. I would bring the people responsible for product, engineering, quality, regulatory and delivery together to establish what is complete, what remains uncertain and which commitments depend on it. The purpose is to make the situation visible enough to decide what happens next.
A schedule can show that an activity is late without explaining why. I want to understand the underlying dependency: a design decision, a test result, an unavailable capability, a supplier issue or competing priorities. Each calls for a different response.
Separate technical uncertainty from disagreement
If the difficulty is technical, define the question the team needs to answer. What evidence would show whether the proposed solution is suitable? Who has the capability to obtain that evidence, and what resources do they need? A bounded investigation can give the programme a better basis for planning.
If people are working towards different priorities, the task is to make those choices explicit. Put the options alongside each other, including what each delivers, what it consumes and what must stop or move. Agreement becomes more useful when everyone can see its consequences.
Make the next decision concrete
For each important issue, I would agree the decision required, its owner and the information needed. A long issue list is difficult to act on when responsibility is shared vaguely or every item appears equally urgent. Start with the issues that prevent other work from progressing.
This discussion should connect engineering choices with user needs, risk, verification and the route to manufacture. In a regulated programme, quality and regulatory specialists need to be part of those decisions so that changes and their evidence requirements are understood.
- What must we decide or demonstrate next?
- Who is responsible for that result?
- What work depends on it?
- When will we review the evidence and update the plan?
Match the plan to available capability
Once the immediate obstacles are understood, test the remaining work against the technical capability, people, time and investment available. Adding people only helps when the work, ownership and interfaces are sufficiently clear for them to contribute.
Where there is a gap, set out the options honestly. That may mean bringing in a particular specialist, changing the sequence of work, revisiting scope or resetting a commitment. The leadership responsibility is to explain what the proposed plan needs and which assumptions could change it.
Review progress through evidence
I would use a short, regular review to examine what has been resolved, what the evidence says and what decision is now required. Keep risks and open points visible, with a clear route for escalation. Recovery becomes tangible when decisions hold, dependencies are resolved and the team can complete useful work with confidence.